Our target is to consolidate and improve the quality and service of existing products, meanwhile constantly develop new products to meet different customers' demands for autoclave machine, boiler accessory ladderChinese boiler ladder, veritcal coal fired boiler, The principle of our company is to provide high-quality products, professional service, and honest communication. Welcome all friends to place trial order for creating a long-term business relationship.
Manufacturer of Coal Fired Steam Boiler - Installation & Technology Service – Double Rings Detail:

Installation Procedure

Step 1. Slag Extruder put into Foundation|
Step 2. Lift Boiler Body to Foundation . Then install the Platform and Stair.
Step 3.Connect Boiler,Economizer (Down Part) and Gas Flue.
Step 4. Connect Economizer ( Up Parts) and Gas Flue.
Step 5.Use asbest rope to Fix Economizer and Gas Flue. Keep no gas leak.
Step 6. Lift Dust Cleaner to Foundation.
Step 7.Connect and fix the Gas Flue between Dust Cleaner and Economizer .
Step 8. Lift I.D Fan to Foundation
Step 9. Connect and fix the Gas Flue between Dust Cleaner and I.D Fan .
Step 10. Lift and Install Chimney , Connect I.D Fan with Chimney.
Step 11. Install F.D Fan
Step 12. Install Coal Feeder
Step 13. Install Reducer
Step 14. Install Valve&Gauge in Boiler Body
Install Valve&Gauge of Economizer
Step 15. Install Steam Distribution Cylinder,connect Main Steam Pipe and Valve&Gauge.
Customer arrange Steam Pipe Route according to the real situation in their factory.
Step 16. Install Water Pump and Valve&Gauge
Customer arrange Water Pipe Route according to the real situation in their factory.
Vertical Style Stainless Steel Water Pump need Vertically Installation.
Step 17. Install the Light,Motor Electric Wire and Electric Control Cabinet
Customer arrange Electric Wire Route according to the real situation in their factory.
Step 18. Install Water Treatment
All Boiler Installation Finish
Steam Boiler Equipment Layout
Note: This Procedure was recommended by Double Rings. Real Operation is according to local situation and Manual.   Photos in the paper is just to display.Real Equipments are subject to actual receipt cargo.

Service after Sale

Service after Sale:
Warrant Time One Year for Whole Boiler without mistake operation after shipment.
Technology Service For life.Customer has any questions about the boiler, our engineers will serve and supply the Technology Service immediately.
Guidance Installation After finish the foundation and boiler arrived in the customer’s factory,two engineers will go to customer’s factory to guidance installation with local workers .
Commissioning After installed, the boiler will be commissioning and training for 2days.
Charge The buyer should provide air tickets with round trip, accommodation, food and local communication and transportation for the engineers, plus the subsidy  for each engineer.

 


Product detail pictures:

Manufacturer of Coal Fired Steam Boiler - Installation & Technology Service – Double Rings detail pictures

Manufacturer of Coal Fired Steam Boiler - Installation & Technology Service – Double Rings detail pictures


Related Product Guide:
Boiler Structure

It is a good way to improve our products and service. Our mission is to develop creative products to customers with a good experience for Manufacturer of Coal Fired Steam Boiler - Installation & Technology Service – Double Rings , The product will supply to all over the world, such as: Liverpool, USA, Seychelles, We integrate all our advantages to continuously innovate, improve and optimize our industrial structure and product performance. We will always believe in and work on it. Welcome to join us to promote green light, together we will make a better Future!
  • Company director has very rich management experience and strict attitude, sales staff are warm and cheerful, technical staff are professional and responsible,so we have no worry about product,a nice manufacturer.
    5 Stars By Gustave from Serbia - 2018.09.21 11:01
    A good manufacturers, we have cooperated twice, good quality and good service attitude.
    5 Stars By Donna from Cambodia - 2017.10.25 15:53
    Write your message here and send it to us

    Related products

    • Super Lowest Price Oil Fueled Boiler - Coal Boiler Chain Grate – Double Rings

      Super Lowest Price Oil Fueled Boiler - Coal Bo...

      More phtos The patent material  RTSiCr,RQTSi4Mo which is our company’s unique material. High temperature resistance, Special process, longer service life.   Travelling type grate stoker Spare Parts—Grate Bar The structure is simple, the metal consumption is small, the ventilation section ratio is large, and the strength and performance requirements of the driving shaft, the driven shaft and the grate are high.

    • High Quality for Oil Steam Boiler - DHL Corner Tube Bulk Water Pipe Boiler – Double Rings

      High Quality for Oil Steam Boiler - DHL Corner...

      Introduction: As a new type of mature high-performance with low-pollution clean coal technology. circulating fluidized bed combustion(CFBC)technology is unlike others that it has a lot of unique characteristics. 1. Circulating fluidized bed is of low-temperature combustion, therefore nitrogen oxides emissions of such boiler is much lower than that of coal-powder boiler, and such boiler could directly desulfurize during combustion process. Circulating fluidized bed boiler with high desulfuriza...

    • Reliable Supplier Boiler Operating - Single Drum Hot Water Boiler – Double Rings

      Reliable Supplier Boiler Operating - Single Dr...

      Parameter : DZG(L)Bearing Pressure Hot water boiler Main Technology Parameter List Model DZG0.7-0.7/95/70 DZL0.7-0.7/95/70  DZG1.4-0.7/95/70 DZL1.4-0.7/95/70 DZL1.4-1.0/115/70 DZL28-1.0/115/70 DZL2.8-1.25/130/70 DZL4.2-1.0/115/70 DZL4.2-1.25/130/70 Rated Capacity T/h 0.7 1.4 2.8 4.2 Rated Working Pressure Mpa 0.7 0.7/1.0 1.0/1.25 1.0/1.25 Rated Steam Temp. ℃ 95 95/115 115/130 115/130 Feed Water Temp. ℃ 70 70 70 70 Fuel Consumption  Kg/H ~150 ~310 ~590 ~900 Thermal Efficiency ...

    • Factory Supply Wood Pellet Boiler - Coal Boiler Biomass Boiler Slag Remover – Double Rings

      Factory Supply Wood Pellet Boiler - Coal Boile...

      Slag Remover used in Coal Boiler Introduction The Slag Remover is a kind of boiler slag tapping equipment. The carbon slag produced after the coal is burned in the boiler is pushed to the slag storage pit by the grate, and is dragged out of the furnace by the slag machine to clear the slag accumulation.  Technology The high-temperature slag discharged from the furnace is first crushed into small pieces by a pair-roller slag breaker, which is convenient for cooling and transportation; th...

    • OEM Factory for Lpg Steam Boiler - Coal Boiler Chain Grate – Double Rings

      OEM Factory for Lpg Steam Boiler - Coal Boiler...

      More phtos The patent material  RTSiCr,RQTSi4Mo which is our company’s unique material. High temperature resistance, Special process, longer service life.   Travelling type grate stoker Spare Parts—Grate Bar The structure is simple, the metal consumption is small, the ventilation section ratio is large, and the strength and performance requirements of the driving shaft, the driven shaft and the grate are high.

    • Newly Arrival High Efficiency Gas Boiler - Biomass Hot Water Boiler – Double Rings

      Newly Arrival High Efficiency Gas Boiler - Bio...

      Introduction : Biomass boiler is horizontal three-back water fire pipe composite boiler. The fuel can be Biomass,coal,wood,rice husk,shells,pellets,bagasse,waste etc.. Display Feature: 1. High thermal efficiency 2. By mechanize operation, reduce intensity of labour of stoker. 3. Easy for installation, when on site, only install slag remover, valve, pipe, water and power, etc., the boiler can be launched into running, additionally, the firing is fast. 4. Easy for installation and moving, save...